Corrective Action for Water Infiltration/Drainage related Deficiencies at Arlington Heights
Corrective Action for Water Infiltration/Drainage related Deficiencies at Arlington Heights
IFB#600-26-14
CLOSED, Awarded
Issue Date:
Jul 7, 2014 11:37 amMeeting Date:
Jul 17, 2014 02:00 pmDeadline Date:
Sep 2, 2014 02:00 pmProcurement Details:
The construction work is estimated to begin in October 2014. The estimated values of the project are in the following ranges General Construction $180,000.00 - $265,000.00 Electrical Construction $4,200.00 - $6,000.00 Plumbing Construction $25,000.00 - $37,000.00 Mechanical Construction $3,000.00 - $4,500.00Contact Information:
Mr. Kim Detrick
(412) 456-5116 Opt #1
Kim.Detrick@hacp.org
HACP Procurement Department
100 Ross Street
2nd Floor Suite 200
Pittsburgh, PA 15219
Question Deadline:
Jul 18, 2014 02:00 pmBid Instructions:
Categories:
Catch Basin/Sewer Clean-Out, Concrete Work, Electrical, Excavation/Hauling, General, General Maintenance, HVAC, Plumbing, Site ServicesProcurement Documents
Jul 7, 2014
Jul 18, 2014
Jul 18, 2014
Jul 24, 2014
Jul 24, 2014
Jul 28, 2014
Jul 28, 2014
Aug 5, 2014
Aug 5, 2014
Aug 6, 2014
Aug 6, 2014
Aug 18, 2014
Aug 18, 2014
Sep 2, 2014